LP Drawing Standards

LP Drawing Standards

LP Drawings

Building Code Review

NBC AE 2023 Building Code Matrix or OBC Building Code Matrix
Building Code Report by Consultant
Major Occupancies
Fire Separations
Travel Distance to Exits
Occupant Load
Mezzanine Conformance
Universal / Barrier-Free Washroom Requirements
Barrier-Free Design Requirements
Plumbing Fixture Requirements (Count)


2023-07 Edmonton Launchpad NBC AE 2023 Code Matrix

  • National Building Code - 2023 Alberta Edition Matrix
#
Item
Response
Ref. Part 3
1
Project Description
New Construction
Part 3
2
Major Occupancy(s)
Group A, Division 2
3.1.2.1.(1)
3
Building Area (m²)
Existing =New = 1 782 m²Total = 1 782 m²
1.4.1.2
4
Gross Area (m²)
Existing =New = 3 018m²Total = 3 018m²
5
Number of Storeys
Above Grade = 2Below Grade = None
3.2.1.1 & 3.2.2.15
6
Height of Building (m)
13.5m
1.4.1.2
7
Number of Streets /Access Routes
1
3.2.2.10 &3.2.5.5
8
Building Classification
Building is Group A, Division 2, up to 2 Storeys, Increased Area, Sprinklered
3.2.2.26
9
Sprinkler SystemProposed
Entire Building
3.2.2.26
10
Standpipe Required?
No
3.2.5.8
11
Fire Alarm Required?
Yes
3.2.4
12
Water Service /Supply is Adequate?
Yes
3.2.5.7
13
High Building?
No
3.2.6
14
Construction
Mixed Construction; Combustible or Noncombustible Construction Used Singly or in Combination
3.2.2.26
14.1
Permitted Construction
Mixed Construction; Combustible or Noncombustible Construction Used Singly or in Combination
14.2
Actual Construction
Mixed Construction; Combustible or Noncombustible Construction Used in Combination
15
Mezzanine(s) Area (m²)
Not Applicable
3.2.1.1.(3)-(7)
16
Occupant loadbased on
Design of BuildingRefer to Code Plans for Posted Occupant Load as well as Building Code Report for detailed occupancy calculations including exit capacity check.
3.1.17
16.1
Occupancy Calc.(O) = Occupancy(L) = Load, persons
Aggregate Occupant Load by Floor:- Level 02 = 220 (L)- Ground Floor = 312 (L)
17
Barrier-free Design?
Yes - Where Applicable.
3.8
18
Hazardous Substances?
No
3.3.1.2.(1) & 3.3.1.20
19
Required Fire Resistance Rating (FRR/FSR/FWR)
FRR of Horizontal AssembliesFloors = FSR & 45 Min. FRR if CombustibleMezzanines = 45 Min. FRR if CombustibleFRR of Supporting Members = 45 Min. FRR or be Noncombustible
3.2.2.26
19.1
Listed Design No(s). or Description (SG-2)
Precast = NBC AE 2023 Appendix D 2.1Wood Loadbearing Partition = ULC W301
20
Spatial Separation
Construction of Exterior Walls - Spatial separation will only be considered facing the property lines, as per 1.3.3.5. Refer to 3.2.3. for per Elevation calculations of Spatial Separation.
3.2.3 & 1.3.3.5
20.1
North Elevation
Noncombustible ConstructionLimiting Distance = >9mProposed Openings = 10%Permitted Openings = Unlimited
20.2
East Elevation
Noncombustible ConstructionLimiting Distance = >9mProposed Openings = 3%Permitted Openings = Unlimited
20.3
South Elevation
Noncombustible ConstructionLimiting Distance = >9mProposed Openings = 10%Permitted Openings = Unlimited
20.4
West Elevation
Mixed ConstructionLimiting Distance = >9mProposed Openings = 3%Permitted Openings = Unlimited
21
Fixture Counts
Assembly OccupancyOccupant Load = 532Male = 266, Female = 266Water Closets Req'd Male = 5Water Closets Req'd Female = 10Total Required = 15Provided 16 Water Closets:Ground Floor- Men's Washroom + Barrier Free WC. 2 WC's + 3 Urinals + 2 BF WC's- Women's Washroom + Barrier Free. 5 WC's + 1 BF = 6 WC'sLevel 02- 4 Gender Neutral WC's
3.7.2.2


2023-13 - LP Markham

Ontario Building Code 2024 Matrix

#
Item
Response
Ref. Part 3
1
Project Description
New Construction
Part 3
2
Major Occupancy(s)
Assembly
3.1.2.1.(1)
3
Building Area (m²)
Existing: NoneNew: Total: 
1.4.1.2
4
Gross Area (m²)
Existing: New: Total: 
5
Number of Storeys
Above Grade: 2Below Grade: 0
3.2.1.1 &3.2.2.15
6
Height of Building (m)
1.4.1.2
7
Number of Streets /Access Routes
3.2.2.10 &3.2.5.5
8
Building Classification
3.2.2.20-.90
9
Sprinkler SystemProposed
Entire BuildingBasement OnlyIn Lieu of Roof RatingNot Required
3.2.2.20-.903.2.1.53.2.2.17
10
Standpipe Required?
Yes / No
3.2.5.8
11
Fire Alarm Required?
Yes / No
3.2.4
12
Water Service /Supply is Adequate?
Yes / No
3.2.5.7
13
High Building?
Yes / No
3.2.6
14
Construction
3.2.2.20-.90
14.1
Permitted Construction
CombustibleNon-combustibleBoth
14.2
Actual Construction
CombustibleNon-combustibleBoth
15
Mezzanine(s) Area (m²)
3.2.1.1.(3)-(7)
16
Occupant loadbased on
m²/personDesign of Building
3.1.17
16.1
Occupancy Calc.(O) = Occupancy(L) = Load, persons
Bsmnt: (O) (L) L01: (O) (L) L02: (O) (L) L03: (O) (L) 
17
Barrier-free Design?
Yes / No (Explain)Explanation...
3.8
18
Hazardous Substances?
Yes / No
3.3.1.2.(1) &3.3.1.20
19
Required Fire Resistance Rating (FRR/FSR/FWR)
Horizontal Assemblies (Hours)Floors Roof Mezzanine FRR of Supporting Members (Hours)Floors Roof Mezzanine 
3.2.2.20-.90 & 3.2.1.4
19.1
Listed Design No(s). or Description (SG-2)
Enter here...
20
Spatial Separation
Construction of Exterior Walls
3.2.3
20.1
NorthComb ConstComb Const cw. Noncomb CladdingNoncomb Const
Area of EBF = m²Limiting Dist = mL / H or H / LFRR = HoursPermitted Max. % OpeningsProposed % of Openings
ListedDesign orDescription
20.2
EastComb ConstComb Const cw. Noncomb CladdingNoncomb Const
Area of EBF = m²Limiting Dist = mL / H or H / LFRR = HoursPermitted Max. % OpeningsProposed % of Openings
ListedDesign orDescription
20.3
SouthComb ConstComb Const cw. Noncomb CladdingNoncomb Const
Area of EBF = m²Limiting Dist = mL / H or H / LFRR = HoursPermitted Max. % OpeningsProposed % of Openings
ListedDesign orDescription
20.4
WestComb ConstComb Const cw. Noncomb CladdingNoncomb Const
Area of EBF = m²Limiting Dist = mL / H or H / LFRR = HoursPermitted Max. % OpeningsProposed % of Openings
ListedDesign orDescription
20.#
Elevation #
For additional walls, add additional rows as required.
21
Fixture Count
Occupant LoadMale = Female = Water Closet(s) RequirementMale = Female = Water Closet(s) ProvidedMale = B/F IncludedFemale = B/F Included
3.7.2.2
22
Other Items
Specify...


OBC 3.1.17.1 Occupant Load

Room Name
Area (m²)
Area Per Person
Calculated Occupant Load
Level 1
Office
10.48
9.30
1
Office
15.47
9.30
2
Lobby
208.33
4.60
45
Lounge
105.99
4.60
23
Bar
57.42
1.20
48
Lounge
91.09
4.60
20
Kitchen
151.64
9.30
16
Staff Room
12.08
4.60
3
Storage
5.67
46
0
Range
994.61
9.30
107
Golf Balls Washing
41.53
46
0
Elec. & Mech. RM
21.40
46
0
IT Room
4.60
46
0
Janitor
4.44
46
0
Beer Cooler
14.68
46
0
Beer Storage
8.02
46
0
Beer Room
7.94
46
0
Level 1 Total
265
Level 2
Lounge
198.59
4.60
43
Range
899.44
9.30
97
Storage
5.67
46
0
Storage
27.05
46
0
Level 2 Total
140
Total Occupant Load
Design Load
305




Number of water closets OBC 3.7.4.3. (1)

Females, Level 01
Occupant Load
Water closet Required
Provided Universal Washroom
Required Barrier-free Water Closet 3.8.2.3.-B
Required Water Closet
133
6
1
1
4
Males, Level 01
Occupant Load
Water closet Required
Provided Universal Washroom
Required Urinal
Required Water Closet
133
3
1
1
1
Females, Level 02
Occupant Load
Water closet Required
Provided Universal Washroom
Required Barrier-free Water Closet 3.8.2.3.-B
Required Water Closet
Unisex Water Closet Provided
50
2
1
0
1
2
Males, Level 02
Occupant Load
Water closet Required
Provided Universal Washroom
Required Barrier-free Water Closet 3.8.2.3.-B
Required Water Closet
Unisex Water Closet Provided
50
1
1
0
0
2


Drawing Scales

Drawing Type
Scale - Imperial
Scale - Metric Equivalent
Key
3/32" = 1'-0"
1:125
Typical
1/4" = 1'-0"
1:50
Enlarged
3/8" = 1'-0"
1:30
Details
6" = 1'-0"
1:5

Dimensioning Standard

All dimensions on this project to have 'double unit' dims, ie Imperial over Metric dimensions.

Required Schedules

  • Doors
  • Door Schedule
  • Door Hardware Groups
  • Door Legend
  • Door Frame Details (Ask Hugo for Reference)
  • Construction Assemblies Schedule
  • Walls
  • Floors
  • Ceilings
  • Roofs
  • Soffits
  • Curtain Wall Elevations
  • Room Schedule w Finishes
  • Interior Finish Schedule
  •  scheduling-type-marks > Interior Finishes Schedule 
  • Tile Weave Pattern Detail (Refer to Heritage)
  • Lighting Fixture Schedule
  • Furniture Schedule
  • Other Hardware Schedule

Enlarged Stairwell Sheets

Drawings for the Enlarged Stairwell Sheets will be combined onto one sheet instead of being separated by series.
Drawing Checklist:
Enlarged Plan at Each Level (Scale 3/8"=1'-0")
Enlarged Section at Through Each Run of Stairs (Scale 3/8"=1'-0")
Annotation List for Each Stairwell Sheet
Stair Path
Riser Count
Dims
Stair Width
Rise
Run
Total Run
Total Rise
Spot Grades
Bottom of Stairs
Top of Stairs
Top of Landing
Handrails
Guardrails
Anti-Slip Stair Nosing

Building Sections

All Sections are to be named by their closest gridline; they must also all face the same direction which is to be plan left or plan up depending on the orientation.

Driving Range Plan

  • Netting Location(s)
  • Indicate Height(s) of Netting on Plan
  • Dim Height(s) of Netting in Section
  • Berming Location(s)
  • Indicate Height(s) of Berming on Plan
  • Spot Grade Top/Bottom of Berming in Section
  • Range Section
  • Building Section
  • Dims and Distance to Targets in Yards

Slab Edge Plans

  • Plans Show Precast Coordination Information Only
  • Precast Panel Sizes
  • Dims for Precast
  • Moment Frames and Locations